BUILT ENVIRONS WA PTY LTD -v- PERTH AIRPORT PTY LTD [No 2] [2019] WASC 76

SUPREME COURT OF WESTERN AUSTRALIA
[2019] WASC 76
N/A
CIV 1513/2016
15 FEBRUARY 2019
KENNETH MARTIN J
12/03/2019
Perth
Defendant's application granted Leave to strike out defective paragraphs of the further amended statement of claim
B
BUILT ENVIRONS WA PTY LTD
PERTH AIRPORT PTY LTD
Practice and procedure
Case management
Large scale construction contract dispute
Prior orders for details to be given via an expert report of deficiencies alleged in drawings and the causative financial loss consequences flowing from each deficient drawing
No sufficient detail of causative financial losses provided
Ongoing refusal to plead global claim or modified total claim
Statement of claim inconsistent with sustained failure to provide details of causative losses arising from each allegedly defective drawing complained of
Leave granted for defendant to apply to strike out defective paragraphs of the further amended statement of claim
Rules of the Supreme Court 1971 (WA)
N/A